Drax gets 100 MW AI data center from 2028 – aims for direct supply from power plant in early 2030s

Drax, Brookfield and Radiant have agreed a plan for a datacentre with an eventual capacity of more than 1 gigawatt at the biomass power station in North Yorkshire.

File photo: File photo of Main Road in Drax village, North Yorkshire, with church and cottages
Drax landsby i North Yorkshire, der Drax biomassekraftverk ligger. (File photo) File photo: Chemical Engineer, CC BY-SA 3.0 · source This adaptation is licensed under CC BY-SA 3.0.

Drax gets 100 MW AI data center from 2028 – aims for direct supply from power plant in early 2030s

Drax, Brookfield and Radiant have agreed a plan for a datacentre with an eventual capacity of more than 1 gigawatt at the biomass power station in North Yorkshire. Yet most of the plan remains hope: phase one is a limited 100 MW, the power will initially come from the grid, and direct supply from the plant lies many approvals away.

Drax power station in North Yorkshire – Britain's largest power station and, according to analysts, the country's largest emitter of carbon dioxide – will, under an agreement announced on 3 November 2026, host a datacentre for AI infrastructure with an eventual capacity of more than 1 gigawatt. Behind the deal stand the plant's owner, FTSE 250 company Drax, together with the investment firm Brookfield and the AI infrastructure platform Radiant, reports The Guardian, citing the companies' own announcement (The Guardian).

What has actually been agreed – and what is vision

The concrete part of the plan is modest. In phase one, Drax will make land and access to the national power grid through existing connections at the site available. The datacentre is planned to be operational from the first quarter of 2028, with up to 100 MW of computing capacity – one tenth of the total vision the companies sketch.

The ambition itself is thus far larger than what is secured. Drax "hopes" to begin supplying the datacentre directly from the power station in the early 2030s, but this depends on regulatory approvals that are not yet in place. The company further claims that the development could attract investment of more than £20 billion – a figure that should be read as a company estimate, not a commitment. No primary documentation, such as a press release or investor filing beyond media coverage, exists in the available material.

Drax chief executive Will Gardiner framed the project as a guarantee of the site's future: according to Gardiner, it will "help secure the site's long-term future and protect hundreds of jobs", while also "supporting the reindustrialisation of the north and strengthening sovereign AI capability" (as reported by The Guardian).

Why now

The timing is no accident. The announcement came a week after the government published a draft national policy statement for datacentres, which stated that they are "as fundamental to our economy as the railways and power grids we have long depended on". At the same time, Drax faces a significant squeeze: from 2027 to 2031, the company will only receive access to half of the current subsidies of £2 million per day, after the government promised that the power station will play a "much more limited role" going forward – against a backdrop of growing scepticism about the company's sustainability claims.

The market reaction was immediate: Drax's market value rose by almost 9% on the London Stock Exchange on 3 November, to almost £3 billion, and the news was well received by equity analysts.

The site's other reality

Drax supplies almost 5% of Britain's electricity by burning wood pellets. The verification of its emissions is contested: according to analysts, the plant is the country's largest single emitter of CO2, but the government does not count these emissions, because Drax claims they are absorbed by trees that grow back. This is an analyst assessment based on contested carbon accounting, not an official classification.

It is precisely this tension that makes the story relevant beyond a single agreement: AI infrastructure's growing power demand is colliding with Britain's most controversial power resource, at the same time as the country's AI ambitions are being made ever more explicitly into national policy.

What will decide whether the £20 billion vision becomes more than a number

In a commentary analysis at Simply Wall St via Yahoo Finance (12 November 2026), some key indicators are highlighted: progress in the public consultation on phase one, which according to the analysis starts in November 2026, and any pre-lease agreements that could show how quickly "this AI infrastructure [build-out]" is moving from plan to contracted revenue streams (Yahoo Finance/Simply Wall St).

The open questions are therefore clear: Will the planning permissions be granted? Will there be an anchor customer committing early? And will Drax actually secure the regulatory approvals needed to supply the datacentre directly from the power station – the part of the plan that can only be realised in the early 2030s, and which is the entire premise for "AI datacentre powered by biomass" to become more than a selling point?

AIMag.no
AIMag.no
The AIMag.no editorial team covers artificial intelligence, tools, research, and regulation.

Get the best of AI MAG in your inbox

News, analysis, and ideas at the intersection of AI and society.